Project Management of Tear off & Re Roofing
Of Nano Science Research Center for
Cushman Wakefield - University of Central Florida Foundation
Orlando, Florida


Client’s Objective:
Review the specifications provided to the Client by the contractor. Assist the Client and the Contractor with scheduling with consideration of the laboratories on the top floor along with
inclimate weather situations. Insure the
installation was completed as per manufactures’ recommendations and project specifications.
Perform Full Time inspections (overnight,
holidays & weekends) and provide daily reports along with photo documentation to the client
during the complete installation process of the Johns Manville Roof Assembly. 



Upon receiving all permits needed in order to begin tear-off and installation of the new roof system, Allied Roofing Consultants worked closely with the Client and Contractor assisting with the scheduling so that no disruptions of any sort were caused to the research laboratories by the installation of the new roof system. Members of Allied performed full time inspections as needed, meeting with a member of the local permitting department while recording
installation progress on a daily basis. All reports were signed and stamped by our in house
engineer to be returned to the Client. 



Project Management of  Repair and Restoration Coating  FBI building


Client’s Objective:

To Extend the life of the roof system.
The modified Bitumen roof white cap was in need of major repairs and was failing in some areas. The roof appeared to have had
multiple repairs over the years.

The building was experiencing major water intrusion and there appeared to be some thermal movement taking place causing the
fiberglass felts to stretch and tear allowing moisture intrusion.
Repairs were needed to repair sealant that was has failed in the tilt up concrete panels as well as the vertical laps and perimeter wall flashings.  Additional fastners were needed in the 1” fiberboard insulation.


The repairs were made to bring the roof system up to the manufacture code prior to
applying the primer and
Solorgard Elastomeric 6083 Coating thus extending the life of the
Roof system.    



Project Management of Repair and Installation Of Sight Screen Walls Boca Raton, Florida

Client’s Objective:
Review and Critique the specificationsprovided to the Client by the contractor. Determine the best course of action toresolve any installation issues. Insure the installation was completed to manufactures specifications. Review contractor bids. Provide photo documentation to the client during the complete installation process of the new sight screen walls.Follow up site visits during the installation as requested by the client. Weekly scheduling Meetings, monitor tenant concerns.

Prior to the start of the sight screen project the consultant met with the client and the contractor to review the engineering of the project to meet with city codes, and set up of the job site as well as with the loading of the materials. The consultant during the course of the
project worked with the contractor to identify possible problems and assisted in finding possible solutions.

The consultant conducted a final inspection of the newly repaired and installed sight screen installation and provided the contractor with a list of items that were to be addressed. This process insures the client that the installation process has been completed to the manufacture’s specifications. During the entire process the client was provided with weekly reports along with photo documentation.